Orpington

 

The South Eastern Railway initiated a through service between London Bridge and Dover, via Redhill and Tonbridge, on 7th February 1844. The route was a circuitous one, the SER being compelled by Parliament to share the lines of the London & Croydon and London & Brighton Railways between the capital and Redhill. It was decreed that only one railway should enter London from the south. Excepting the ongoing bickering between the respective companies over track access, the additional mileage of this detour did not become problematic until the advent of the ‘’East Kent Railway’’. Renamed the ‘’London Chatham & Dover Railway’’ in 1859, this company eventually forged a shorter route between Victoria and Dover via Chatham, through services commencing for the line’s entirety on 22nd July 1861. The ‘’Chatham’’ main line became an attractive alternative to the older Redhill route, thus the SER was in need of a plan to prevent losing most of its London to Dover traffic to its new rival. The solution was to shorten the London Bridge to Dover route by means of a cut-off line, avoiding Redhill and providing a more direct route between the capital and Tonbridge. Parliament authorised the line on 30th June 1862, for passage via Chislehurst, Orpington, and Sevenoaks, taking 12½ miles off the original journey length. The line was commissioned in stages: the St Johns to Chislehurst section came into use on 1st July 1865; on 3rd February 1868, the line formally opened to freight traffic for its full extent to Tonbridge, but passenger services were only extended as far as Sevenoaks on 2nd March of that year. Through running to Tonbridge for passenger traffic commenced on 1st May.

A station at Orpington came into use with the Sevenoaks section of the cut-off line on 2nd March 1868. It started life as a typical SER rural outpost, comprising two platform faces either side of a double-track. These surfaces lied directly opposite each other, unlike those at a number of stations along the route, which were staggered in nature. The main building was positioned on the ‘’up’’ side, and was a standard SER economical affair, being single-storey and clapboard in construction, complete with a slated pitched roof. It was matched on the ‘’down’’ platform by a structure of similar size and appearance, and both buildings were equipped with flat-roofed canopies. The latter were graced with the standard clover-patterned SER valance, which can still be seen in evidence today at Maidstone West. The platforms were linked by a subway (a common feature of those stations which were built upon embankments, where walkways could be excavated more easily), positioned immediately to the south of the station structures. The subway entrances were provided with brick surrounds, complete with curved roofs, identical to those which are still extant at Bexley and Northfleet stations. Both platforms were lined at their rears by wooden fencing, a practice which is still in use today at Pluckley, and gas lamps were of the typical diamond-shape design. There were no goods facilities at this station from the outset, but during the first half of the 1890s, a single northward-facing siding was incorporated. This trailed off the ‘’up’’ track at about ten degrees to the running lines, and terminated behind the ‘’up’’ station buildings.

The formation of the SE&CR on 1st January 1899 heralded significant improvements for the Tonbridge cut-off line, and indeed, the suburban railway operation on ex-SER and ex-LC&DR networks in general. In 1900, work commenced on linking the ‘’Chatham’’ main line with the ex-SER cut-off route, by means of installing connecting loops, a task which was fully complete by 19th June 1904 (see the Chislehurst Junction section). In the meantime, significant earthworks had begun in the effort to upgrade the St Johns to Orpington section of the Tonbridge cut-off line from double to quadruple-track operation. This involved extensive rebuilds of stations at Hither Green, Grove Park, Chislehurst and Orpington, and the provision of a new set of platforms at Elmstead Woods. Four-track running for scheduled services commenced between St Johns and Elmstead Woods on 18th June 1905, but this was preceded by the commissioning of the quadruple-track section between Elmstead Woods and Orpington on 6th June of the previous year.

All traces of the SER’s Orpington station were swept away during the improvement works. Extensive earthworks produced a wide cutting upon the existing station site to accommodate a completely new layout capable of serving an intensive four-track suburban and main line operation. The entire quadrupling scheme formed part of the SE&CR’s desire to improve its commuter operation, which included increasing service frequency and introducing new through trains between ex-SER and ex-LC&DR networks. Orpington marked the end of the London commuting zone on the Tonbridge cut-off line: four tracks converged into two beyond the southern end of the station, and provision was made to keep terminating suburban services out of the paths of those main line services continuing on into Kent. Four through platform faces were created, each some 750-feet in length, and these were flanked on either side by a northward-facing bay line for terminating commuter services. The ‘’up’’ and ‘’down’’ side bay platforms measured 495-feet and 575-feet in length respectively. This arrangement produced three main platform surfaces, one of which was a centrally-located island. W-shaped canopies appeared on all surfaces, these being supported upon iron frames and demonstrating the intricate clover-patterned valance originally introduced by the SER. The canopies appear to have been used as the design basis for those plainer W-shaped designs employed by the Southern Railway during station modernisations and rebuilds throughout the late 1920s and 1930s, on all divisions of the company’s network (see Tonbridge and Swanley). The island canopy measured 295-feet in length, whilst the presence of station structures on both side platforms saw that the respective canopies on these surfaces were longer, extending for 325-feet. The platforms were gas lit with the then customary diamond-shaped lamps, as per the former station of 1868, and all surfaces were linked by a subway.

Orpington’s main building, like that of the original station, was positioned on the ‘’up’’ side, and was served by the very same approach road as the SER clapboard structure. The replacement station had been built throughout in crème brick: the ‘’up’’ building was single-storey, complete with a slated pitched roof, and measured 110-feet in length, which included a small appendix attached to its southern elevation. It was also in the company of a smaller crème brick single-storey structure to its north; this measured 55-feet in length, but was physically detached. Finally, the main building’s approach road elevation was protected by a 42-foot long canopy, which demonstrated the same valance pattern as the main platform structures. The ‘’down’’ side was also host to a singe-storey crème brick structure; this was, in effect, a scaled-down version of the aforementioned example on the ‘’up’’ side, and like its larger counterpart, it was host to a porch canopy on its road-facing elevation.

 


Orpington SE&CR

 

Track plan of rebuilt SE&CR layout. Drawn by David Glasspool
 


26th September 2004

 

Orpington

Platforms 7 and 8 are the newest, having been incorporated as part of the 1992 station modifications.

They replaced a trio of sidings. A further giveaway sign that this platform is of a different era to the

others is its canopy, rectangular in appearance rather than W-shaped like its counterparts. ''Networkers''

Nos. 465033 and 465202 are seen stabled in the bays on 26th September 2004. David Glasspool

 


26th September 2004

 

Orpington

A London-bound view shows the EMU sidings, covered until 1992 by the largest carriage shed on

the Southern Region. For most of its length, the carriage shed did not feature a third rail. In more

recent times, overhead gantries supporting lighting have appeared over the sidings. This is the scene

on 26th September 2004. David Glasspool

 


26th September 2004

 

Class 465s at Orpington

A BREL product alongside a GEC build: on the left is Class 465 No. 465006, just about to depart

for London, whilst stabled in the bay platform is Class 466 No. 466033 (the latter pairing with a

Class 465 in NSE livery). The blue and yellow livery of No. 465006 was reached by simply applying

vinyl over the existing NSE livery, hence the cab ''flashes'' of the latter are still evident. The vinyl

coating was part of a leftover batch from the Class 365 livery applications. David Glasspool

 


 

Next: the History Continues >>

 


Return to the Kent Rail Homepage or alternatively, check for Updates.

Website & Copyright information - Links - Contact the Webmaster


 

All content is copyright © David Glasspool