Tonbridge
This has for long
been an important interchange station, sandwiched in-between junctions for Dover
and Hastings to the east, and alternate routes to the capital to the west.
Serious proposals for building a railway between London and Dover were made in
1825, and in that year, surveys of the County of Kent were made. Further
surveying took place in 1832 and 1835, specifically the northern territories of
the county, but problems were soon brought to the fore. No support for the
scheme came from inhabitants of the towns within the northern parts of the
county, and fierce, universal opposition to the railway came from landowners. In
a ‘’General Statement of Projects’’ later published by the South Eastern Railway
in 1846, it was recounted that of the railway, the ‘’system was not understood
either in or out of Parliament. The powers of the Locomotive were little known,
and it appeared that, to obtain in that direction the gradient then considered
as the maximum surmountable by the engine, enormous expense must be incurred.
The capacity of a Railway to compete successfully with the parallel Steam
Navigation had not been brought to the test, and the results of such a
competition were distrusted.’’ [South Eastern Railway: General Statement of the
Position and Projects of the Company 1845 – 6].
The beginnings of the Dover trunk line lie with the London & Croydon Railway,
formed by an Act of Parliament on 12th June 1835 to construct a line between its
namesakes. This scheme met with little opposition, for the proposed route
followed the course of a failed canal and did not make any incursion onto
important private property. The line was subsequently built at a cost of
£615,160 (£53,000,000 at 2008 prices), and was formally opened to traffic on 1st
June 1839. For a matter of days, trains ran into the London & Greenwich
Railway’s London Bridge station, until a dedicated terminus was provided on 5th
June. The southern end of the route terminated at today’s West Croydon.
Parliament decreed that only one railway should access London from the south,
which meant that promoters of lines to Brighton and Dover had to use the L&CR as
an outlet. The scenario was two-edged: firstly, sharing of one route by numerous
companies would lead to obvious capacity problems and conflict of movements;
secondly, however, much expense would be spared, for the first nine miles of
line from London was already complete. Promoters of the South Eastern Railway,
from London to Dover, first deposited a Bill in 1836 for a line which left the
then proposed South Western Railway at Wandsworth. This would subsequently cut
across south London to Croydon, where the existing line from London Bridge
terminated. This was met with unwavering opposition from Parliament, which
maintained that only a single rail outlet south of London was permitted. Thus,
promoters revised their plans to begin the new Dover main line at Croydon, at
the end of the L&CR.
A start point of Croydon naturally laid the foundations for a Weald of Kent main
line. In contrast to the towns in the northern parts of the county, districts
and influential landowners situated around the course of the proposed line
strongly supported the railway. The line would cut through the central part of
the county in a straight line, neatly positioned halfway between the Thames and
English Channel. The line would also be characterised by shallow gradients, for
the chosen route traversed the natural level. The ‘’South Eastern Railway Act’’
received Royal Assent on 21st June 1836. The company was authorised to raise a
joint-stock capital of £1,400,000 (£110,000,000 at 2008 prices), and could take
out loans totalling an additional £450,000 (£35,300,000 at 2008 prices). The SER
Bill did not pass without competition, and two alternate independent railway
schemes were also promoted at the same time. The first of these was the
‘’Central Kent Railway’’, which proposed a line from Deptford to Sandwich,
passing over Cray, Darent, Medway, and Stour Rivers en route. The line was
characterised by heavy earthworks and notable gradients, putting it at a
distinct disadvantage to the SER scheme. A 4½-mile-long cutting, with average
depth of 50-feet, was required at Wrotham; a second cutting, 3-miles and
16-chains in length and with an average depth of 21-feet, would have to be
excavated at Charing. A lofty viaduct would be required over the Medway, and
five heavy embankments were required, the latter of which were namely:
Sandwich Embankment: 5¾-miles in length, with an average height of 18-feet
Medway Embankment: 1-mile in length, with an average height of 55-feet
Aylesford Embankment: 3-miles in length, with an average height of 35-feet
Darent Embankment: 2-miles 5-furlongs in length, with an average height of 36-feet
North Cray Embankment: 1-mile 5-furlongs in length, with an average height of 58-feet
The second
scheme was that of the ‘’North Kent Railway’’ (not to be confused with the later
‘’North Kent Line’’ of the SER), which proposed a line commencing nearby
Hungerford and Waterloo Bridges in London, to Dover, via Blackheath, Woolwich,
Gravesend, Rochester, Chatham, Sittingbourne, and Canterbury. Branches would
also be sprouted to Deal, Maidstone, Sheerness, Faversham Quays, and Chilham, in
addition to making a connection with an already authorised line to Ramsgate and
Margate.
Construction of the Weald of Kent Line was slow to start, work finally
commencing on 25th November 1837. The line began at Reigate, and the SER
appointed William Cubitt as engineer. Works at Tunbridge commenced in the same
month, and the first rails were delivered in May 1841. By 20th November of that
year, three miles of finished line existed between Edenbridge and Tunbridge, and
track laying between the latter and Staplehurst was also well-advanced. On 26th
May 1842, through running between London Bridge and Tunbridge via Reigate
commenced. Services were extended eastwards to Headcorn on 31st August of the
same year, to Ashford on 1st December, and then onto a temporary station in Folkestone on 28th June 1843.
On completion of Foord Viaduct, a permanent Folkestone station was brought into
use on 18th December 1843 and, finally, through running to Dover began on 7th
February of the following year.
The strategic importance of Tonbridge (as it is now known) is reflected by the
fact that your author first needs to mention two more railway lines before the
subject of the station itself is tackled. The first is the direct line to
Hastings: Royal Assent was received for a branch from Tunbridge to Tunbridge
Wells on 31st July 1845, a length of 4-miles 1-chain. A capital of £180,000
(£14,500,000 at 2008 prices) was authorised, with the option of taking out a
further £60,000 (£4,840,000 at 2008 prices) in loans. The line was specified as
single-track, but midway through construction, the decision was taken to double
it throughout. On 18th June 1846, the SER received Parliamentary approval for
two extensions of this line, the first being a 25¾-mile stretch from Tunbridge
Wells to Hastings, authorised at a cost of £640,000 (£46,200,000 at 2008
prices), with the option of taking out loans of £213,000 (£15,400,000 at 2008
prices). The second line was from Hastings to Rye, 5¾-miles in length, of which
£20,000 (£1,440,000 at 2008 prices) was the authorised capital, in addition to
loans of up to £6,600 (£476,000 at 2008 prices). These sums also included the
construction of a spur to Rye Harbour, 1¾-miles long.
Tonbridge: 1895
An Ordnance Survey from 1895 shows the station before the southern bay platform was converted for through running. The engine shed, to the right, is situated within the fork of the diverging Ashford and Hastings lines. To the left, the line through Sevenoaks veers northwards, whilst that to Redhill continues on an east to west heading. Click the above for a larger version.
28th July 1949
''R'' Class No. 1703 (by this time BR No. 31703) was observed in the ''down'' platform loop at Tonbridge. The engine was still wearing the last carnation of the Southern Railway livery, complete with an ''S'' prefix before its number. The station canopy behind the locomotive dated from 1935 rebuilding work. © David Glasspool Collection
28th July 1949
The fireman is seen refilling ''H'' Class 0-4-4 No. 31543 with water in the ''down'' platform loop. At this time, the engine still wore Southern Railway livery with ''Sunshine'' lettering. Behind the engine can be seen the distinctive end of an ex-SE&CR ''Birdcage'' carriage. © David Glasspool Collection
1957
An Unrebuilt Bulleid Pacific rounds the curve at the west end of the station, fronting a named Victoria to Dover boat train via Orpington. The engine retains a high-sided tender, and a couple of Blood and Custard Bulleid-designed carriages can be seen trailing behind. The white signal posts just left of centre are on the throat of Tonbridge West Yard, and the sturdy SR-built ''A'' box is on the right. The sidings behind the Bulleid Pacific and in the immediate foreground can be seen holding ex-SE&CR ''Birdcage'' stock. © David Glasspool Collection
Next: The History Continues >>
Return to the Kent Rail Homepage or alternatively, check for Updates.
Website & Copyright information - Links - Contact the Webmaster
All content is copyright © David Glasspool unless otherwise stated