Folkestone Harbour
This is an interesting and characterful branch line, with a varied history. The
story begins in 1807, when Royal Assent was received for the incorporation of
the ‘’Harbour Company’’ to construct an extensive harbour at Folkestone, using
finance provided by the Government’s Loans Commission. Construction began in the
following year, and Scottish-born Thomas Telford acted as consulting engineer.
Telford had previously been involved in the enlargement of Somerset House (The
Strand, London), and had also engineered canals and roads in Shropshire.
However, Parliamentary approval of the Folkestone Harbour project had originally
been passed on the basis of a design developed by West County-born engineer
William Jessop. Amended plans outlined a harbour of 14 acres in extent, a
scaled-down figure from the original proposals. The formation of a harbour at
this location had been helped by the presence of an existing spit head of
shingle which partly formed the desired shape.
Twelve years were to pass before the project was deemed complete. The harbour
walls were formed by laying two parallel rows of stone slabs, angled inwards at
45 degrees. The gap in-between the rows of slabs was subsequently in-filled with
crushed stone. Three walls – or, rather, piers – were formed during the
construction: West, South, and East. The former two were, essentially, two of
the same thing, for the pair were joined together at right angles to form an
L-shape harbour wall to the south. The East Pier was constructed for the purpose
of protecting the harbour from incoming winds from this direction, and its
presence created an enclosed body of water, accessed by means of 120-foot gap
between it and the South Pier.
Wall Lengths
The disadvantage of having a trapped body of water soon became apparent, as the
current of the English Channel carried silt into the harbour, where the deposits
settled. The Harbour Company deemed the silt removal process as too expensive,
but this decision soon put paid to the profitability of the operation, and in
1842, the company went bankrupt.
In the meantime, railway expansion from London had been in full swing. The
London & Greenwich Railway had commenced operation between Spa Road and Deptford
on 8th February 1836, and in the same year, the South Eastern Railway (SER) was formed. The latter had received Royal Assent for the
construction of a Weald of Kent line to Dover, branching off the existing London
& Croydon and London & Brighton Railways’ metals at Redhill. The company
commenced operation between London Bridge and Tonbridge on 26th May 1842, and
this was followed by the opening of an eastward extension to Folkestone on 28th
June 1843, the line initially terminating at temporary accommodation. A
permanent station, named ‘’Folkstone’’ (note the missing ‘’e’’) was opened to
traffic on 18th December 1843, after the completion of the impressive Foord
Viaduct. The latter comprised nineteen arches, the tallest reaching 100-foot
high, and took half a year to complete. In conjunction with the viaduct works
and the opening of a new station site, the SER bought out the bankrupt
Folkestone Harbour operation, and was eager to commence steamer services across
the English Channel. Unfortunately, as a condition of the original 1836 Act of
Incorporation, the company was forbidden to run a passenger boat operation to
the Continent. To bypass this obstacle, the SER, and, indeed, other railway
companies, established nominally independent concerns to run the steamers.
On acquisition of the harbour in 1843, the railway company began constructing a
1325-yard-long double-track branch line, descending at a gradient of 1 in 30,
towards the water. This terminated at a coal jetty, and had a trailing
connection with the incoming line from London. A peculiar characteristic of this
branch from the outset was that it could only be accessed from the main line by
means of a head-shunt manoeuvre into sidings. The SER’s jetty was originally
constituted of a brick viaduct, of which twelve arches spanned the water for the
majority of the harbour’s north to south width, and ran parallel with the west
pier. The viaduct accommodated a double-track, and flanking the structure on
either side were wooden additions which were each host to a single line – thus,
in total, four tracks ran parallel with each other across the water here. The
viaduct seemingly terminated in limbo, for there was a 150-foot gap between it
and the southern pier. Behind the southern pier existed the aforementioned
shingle spit; ultimately, the SER was to fill the breach and take the line over
the remaining stretch of water, and establish extensive goods and passenger
facilities upon the site. This the company did in 1847, and to permit continued
access by boats to what had become the ‘’Inner Harbour’’, a swing bridge was
built within the 150-foot gap. This rested upon a centrally-located brick
support, and rotated upon an axis much in the same fashion as an aircraft
propeller.
From 1843 onwards, when railway operation down the branch first commenced,
through to 1847, when the line was fully extended over the whole width of the
harbour by means of the earlier-mentioned swing bridge, the SER undertook a land
reclamation task, which sought to extend the width of the shingle spit head
southwards. Not only would this allow the construction of a terminus station and
a large warehouse within a maze of lines, but it also laid the foundations for
the construction of yet another pier. Passenger services to Folkestone Harbour
commenced on New Years Day 1849, but only temporary arrangements were in place
on the southern side of the water, as construction of the terminus was still
ensuing. Completion of the station came in the following year: this became a
two-platform northward-facing affair, serving a double-track and demonstrating
an overall roof. 70 yards to the east of the station existed a rail-served goods
warehouse, measuring 180-feet in length by 90-feet in width. A pair of spaced
out tracks entered the building, the two being fed directly by small wagon
turntables.
Folkestone Harbour station, as rebuilt by the SER during 1893, and after SE&CR enlargements of 1905. Drawn by David Glasspool
Great War
Ex-SER 0-6-0 ''R'' Tank No. 342 is seen in Folkestone Harbour carriage sidings, which were located west of the platforms and required a reversing manoeuvre to access. No. 342 was built in 1889 and withdrawn in 1931; the livery worn was that applied by the SE&CR during World War I, which at least helps to date this view. This photograph has been submitted by Dennis Nelson and shows his Great Grandfather, Robert Peters, in the engine's cab, on the right. He was an engine driver for the SE&CR and, subsequently, the Southern Railway. © Dennis Nelson Collection
1960
Pannier power: a pair of former Western Region ''5700'' Pannier Tanks are seen commencing the tough climb up the Harbour branch, with a boat train in tow. These engines replaced the native ''R1'' Class locomotives in the Folkestone area in the year prior to this photograph. The Late Brian Relf, © Colin Relf
1961
A view across the harbour shows a brand new 4 CEP unit, wearing all-over BR(S) Green, departing the ''up'' platform. To the right of the unit can be seen the SE&CR signal box and a line of vehicles, the latter held up by the level crossing. © David Glasspool Collection
Next: the History Continues >>
Return to the Kent Rail Homepage or alternatively, check for Updates.
Website & Copyright information - Links - Contact the Webmaster
All content is copyright © David Glasspool unless otherwise stated