Northfleet
Crossrail
This interesting site
had for long been involved with cement production, an association which was
brought to a close in December 2008 with the decommissioning of the Northfleet
Works. This was due to exhaustion of chalk from Eastern Quarry, the works’ main
supply source which resided about a mile to the south west. The end of an era
was marked by the ceremonial demolition of the twin 550-foot-tall chimneys on
28th March 2010. The cement works dated back to 1969, when it was commissioned
by APCM to replace a number of older complexes nearby. APCM was rebranded ‘’Blue
Circle Industries’’ in 1978, and this company was absorbed into the empire of
French-owned ‘’Lafarge’’ in 2001.
In March 2009, Lafarge submitted an application to Kent County Council for
permission to operate a bulk aggregates import terminal at the former cement
works site. This was to handle up to 3,000,000 tonnes of material per annum,
most of which would be crushed rock, the rest being marine-dredged aggregate.
Materials would be brought in by boat and unloaded onto an existing operational
wharf of 978-foot length and 42-foot depth. These loads would subsequently be
dispatched onwards by road and a renewed rail link. With reference to the
latter, this had formerly been a merry-go-round loop for the cement works, which
made a connection with the North Kent Line to the north west of Northfleet station.
Sidings once existed behind the ‘’up’’ platform of the latter, and access to the
cement works was afforded by two tunnels (‘’Western’’ and ‘’Eastern’’) bored
through a chalk ridge, enabling a link-up with British Rail metals. There also
existed a third tunnel to the west, which allowed road access.
Gypsum trains last ran over the MGR loop on 19th March 1993, but the track
remained in situ thereafter, most of it subsequently being lifted by ‘’Union
Railways’’ in connection with Phase 2 of the Channel Tunnel Rail Link (CTRL).
Under the CTRL Act, Union Railways had an obligation to reinstate key parts of
the former MGR loop. This extended to those rails which followed the alignment
of the previous arrangement; the obligation did not cover those new sidings upon
the former cement works’ site, or track within Church Path Pit which deviated
from the original course of the old layout. No additional rights were needed to
re-establish sidings behind the ‘’up’’ side of Northfleet station. The
reinstated rail link was not to form a loop as per the previous arrangement, and
only Eastern Tunnel would receive track, although Western Tunnel would still be
cleared. Hitherto, both tunnels had been blocked up since the cessation of
gypsum operations. Track laying in Church Path Pit commenced in July 2009.
In June 2011, ‘’Crossrail’’ reached a lease agreement with Lafarge to take over
part of the former 104-acre Northfleet Cement Works site. It was proposed to use
the area for the temporary storage of spoil excavated from Crossrail tunnelling
operations between Royal Oak and Farringdon. Construction of the tunnel portal
at Royal Oak began in January 2010 and was completed in September of the
following year. On Thursday 3rd May 2012, tunnel boring from Royal Oak started,
involving the driving of twin bores under Central London, each 6.4 KM
(3.98-miles) in length. The fact that the waste spoil from these operations
could be transported away by sea from a deep water wharf at Northfleet, after
delivery by rail, was a major reason why the former cement works site was chosen
by Crossrail.
Reinstating the railway link between the Northfleet site and the North Kent Line
was priced at £13,000,000, and Lafarge appointed ‘’Balfour Beatty’’ as the main
infrastructure contractor for the project in July 2011. The works included the
laying of nearly three miles of new track, extending for just over
1½-route-miles, in addition to re-signalling on the North Kent Line in the Northfleet vicinity. ‘’Arrival’’ and ‘’Departure’’ loops were laid behind the
station’s ‘’up’’ platform and a series of illuminated bollards installed between
them, to light a central walkway. A single-track curved approach towards an
unblocked and well-lit Western Tunnel was laid within Church Path Pit. At the
portal, a northward-facing siding was provided, and a double-track formation was
carried through the tunnel. On the northern side of the chalk ridge, the link
widened to three tracks, which were laid immediately west of a huge ‘’Bulk
Powder Import Terminal’’. The triple track formation was extended northwards and
curved round to run parallel with the adjacent river. The line was protected on
either side by 1.8-metre-high palisade fencing and linked to the wharf by an
enclosed conveyer belt. To meet port security regulations, the wharf has been
equipped with 2.4-metre-high fencing.
2nd August 2009
A view of a sunny Church Path Pit reveals the two CTRL sidings in the background, feeding off the spur from Ebbsfleet International. In the foreground can be seen the newly laid single-track line bound for the cement works. At this time, the track terminated at the then still blocked-up portal of Eastern Tunnel, and the Crossrail lease agreement was nearly two years away. © David Glasspool
2nd August 2009
At the time, the line was physically isolated from CTRL metals, but a three-way set of points had already been formed, feeding off the two CTRL sidings. As will become clear in the later pictures, this was not used as a connection for the cement works' spur. In the above view, there are rails on three levels: those in the foreground, within Church Path Pit; the single track behind, which ascends to the North Kent Line; finally, at the very top, the North Kent Line itself. © David Glasspool
Return to the Kent Rail Homepage or alternatively, check for Updates.
Website & Copyright information - Links - Contact the Webmaster
All content is copyright © David Glasspool unless otherwise stated