Folkestone Harbour
In 1893, a comprehensive rebuild of the site began, involving the demolition of
the original terminus station and the creation of a through affair. Two
platforms were built around a tight curve, which eventually gave the line a
south-easterly heading towards a timber-built pier. The latter jutted out from
the shingle spit and was served by a single-track from the goods sidings.
Stone-faced single-storey offices appeared on both platform surfaces, and these
in turn were fronted by ornate V-shaped platform canopies. Built on a lattice
iron frame, the canopies demonstrated the typical SER clover valance design (an
example of which can still be seen in existence at Maidstone West). The
platforms were linked by an enclosed lattice footbridge, which was to the same
design as that still in evidence at Maidstone West, and intercepted the canopies
at their halfway point. A second, exposed lattice footbridge was also erected at
the northern extremity of the station site, adjacent to the level crossing.
As part of the revisions, the goods yard to the east of the platforms was wholly
revised and enlarged, and consequently, the aforementioned warehouse became
sandwiched within a maze of tightly curved sidings. Over twenty-five sidings
eventually appeared at the harbour site (including carriage berthing facilities
west of the platforms), three of which entered the warehouse. The majority of the goods
yard required a reversal manoeuvre to gain access: locomotives would proceed
through the Harbour station platforms, and on reaching their ends, would be
presented with a trailing junction. Here, goods and carriage sidings converged
with the platform lines, and both sets of metals lead to a head shunt upon a
timber-fabricated pier. As part of the same works, piecemeal rebuilding of the
pier from wood to concrete began, and overall lengthening of the structure also
occurred. A single SER-designed all-timber signal box was in evidence at
station: this was positioned upon the southern end of the ‘’up’’ platform and
controlled the junction between the platform lines and the carriage sidings. A
second signal box, again of SER design, could be found on the northern side of
the inner harbour water, built upon a brick pier jutting out from the west side
of the railway viaduct.
The continued southerly extension of the pier, coupled with the rebuilding of it
in concrete, gave rise to a second station. A single wooden-fabricated platform
was erected alongside the ‘’up’’ track, south of the existing station, in 1905.
It was physically detached from the harbour station, being separated from the
latter’s ‘’up’’ platform by the single-track trailing connection from the
carriage sidings to the west. The platform was protected by a flat-roof timber
canopy, demonstrating the familiar clover-patterned valance. The two sites were
connected by a lengthy exposed metal footbridge, and access to the pier required
the payment of a toll. A second signal box was opened to control the complex
arrangement of tracks upon the extended pier.
Circa 1915, track revisions took place at the northern end of the site, which
involved removing the ‘’down’’ track wagon turntable sandwiched in-between the
level crossing and the platform ends. A new signal box came into use upon the
northern end of the ’’up’’ platform: this was built by the SE&CR, but clearly
derived its design from those earlier cabins erected by contractor Saxby &
Farmer. Complete with a brick base, timber upper half, and pyramid-shaped roof,
a much larger example, but of the same ilk, came into use with the newly built
Dover Marine terminus in February 1915.
Under the Southern Railway, changes at Folkestone Harbour were substantial.
These commenced in 1930 with the removal of the lattice-patterned swing bridge
across the inner harbour entrance. This was replaced by a heavier and more
robust single-span steel bridge, which could support greater weight. The
strengthened swing bridge would indeed have been immediately useful, for during
the same decade, the SR tested the use of ''W'' Class 2-6-4 and ''Z'' Class
0-8-0 engines on the harbour branch. These were powerful locomotives, which were
able to haul heavy loads up inclines and negotiate flying junctions with ease.
However, restricted clearances put paid to their continued use on the Harbour
line, and banking engines remained in the form of the 1910-introduced 0-6-0 R1
Class. The greatest of the SR’s works at the site commenced in 1938: the
‘’down’’ Harbour station platform was extended southwards, virtually doubling
its length, and bringing its southern end in line with the sea end of the
isolated pier platform. This produced a platform measuring about 215 yards in
length, protected by a steel-framed canopy with a plain timber valance. The gap
in-between the wooden pier platform and the Harbour station’s ‘’up’’ surface
could not be in-filled to produce a similarly-long area, because between the two
was the single track trailing connection with the carriage berthing sidings. As
a consequence, the somewhat unusual arrangement of having a single, elongated
‘’down’’ platform, combined with two separate ‘’up’’ platform sections, was
retained. At the southern extremities of both the ‘’down’’ and pier platforms,
an enclosed concrete footbridge was installed. The enclosed lattice footbridge
of SER origin, within the confines of the original Harbour station, had been
removed in 1920, under SE&CR auspices.
The British Railways era witnessed the coming of the Western Region to Kent. In
1959, the elderly R1 Class tank engines, which had served the Folkestone Harbour
branch well, were replaced by ex-GWR Pannier Tanks. Of the ‘’5700’’ series,
these engines ran off Folkestone Junction shed, and remained on banking duties
along the line until the last examples were re-allocated to Nine Elms and
Salisbury sheds in November 1961. On 18th February of the following year, new
colour light signalling was introduced as part of ‘’Phase 2’’ of the Kent Coast
Electrification scheme. This system was controlled by a then new power box
installed at Folkestone Junction; the SE&CR cabin at the northern end of the
Harbour station remained in use to operate the level crossing and the points of
the platform lines. The full accelerated electric timetable along the ex-SER
Weald of Kent route, via Tonbridge and Ashford, commenced on 18th June 1962.
Goods facilities were withdrawn on 17th August 1968, resulting in the lifting of
all those sidings east of the station. The cessation of steam-hauled services
had also made the carriage berthing sidings to the west of the platforms
redundant, and their removal finally allowed a substantial southward extension
of the ‘’up’’ platform. This became significantly longer than the ‘’down’’
platform, and was ultimately extended to the end of the concrete pier, complete
with a simple upward-slanting glazed canopy. It is worth noting that at the
southern end of the ‘’down’’ platform, the layout narrowed to single track, and
third rail was not extended beyond this set of points.
In 1980, an enclosed transparent footbridge was erected over the top of the
station, just south of where the long-gone SER lattice footbridge would have
resided. This provided the ‘’up’’ platform with a direct link to the passenger
ferry terminal situated immediately adjacent the ‘’down’’ side of the station.
Folkestone Harbour continued to be served by regular boat trains for many years
and indeed, outlasted its counterpart Dover Western Docks (Marine) when this
closed in 1994, in response to the opening of the Channel Tunnel. Despite
surviving closure, boat traffic to the Harbour station was drastically reduced,
and in its final days it only had two scheduled connecting services: one from
Charing Cross, connecting with the 11:15 Sea Cat service to Boulogne, then
another at 13:15, connecting with the return working. With the transference of
the Sea Cat to Ramsgate in September 2000, rail services to the Harbour station ceased,
such occurring shortly before the Summer 2001 railway timetable came into use. The third
rail was de-energised later on in the same year and the track work subsequently
deteriorated to the extent that the ''up'' line was taken out of use. Reviving
fortunes seemed to occur in May 2002 with the installation of TPWS along the
branch, but the rails of the ''up'' line were later lifted, although charter
services did soon commence. In April 2006, new plans were published showing a
total redevelopment of Folkestone Harbour. This included the conversion of the
whole harbour site into a marina and the permanent closure (and presumably,
demolition) of the railway branch.
Folkestone Harbour: Life after Death
The closure date of this station was for some time not clear and when a particular
service seemed to be the final one, another event appeared on the schedule! The
last VSOE service was originally scheduled for 9th November 2006, followed by
the final train of the year - in the form of the ''Blue Pullman'' - on 14th
December. A stay of execution was granted and a steam-hauled charter
ran on 27th January 2007. On 12th April 2008, it really did seem like the end of
the line for the Folkestone Harbour branch: a final steam-hauled charter,
fronted by Bulleid Light Pacific No. 34067 ‘’Tangmere’’, ran to mark the
ultimate closure of the line, and this service was followed by a trio of Class
73 Electro-Diesels (Nos. 73204, 73205, and 73209) traversing the route. However,
despite this ''final'' closure event, VSOE services continued to use the Harbour
branch every Thursday and Sunday, running from London Victoria. With Network Rail receiving
a number of objections to shutting the branch from rail bodies, including
the Department for Transport, perhaps this prolonged the closure process. The original intention
was to concentrate VSOE services at an improved Folkestone West station.
1984
The tide was in when this BR Blue Class 33/2 was seen drifting over the famous harbour viaduct with the VSOE (or, rather, British Pullman) from London Victoria. The British Pullman made its debut in April 1982, the first trip being a one-off run between Victoria and the Sussex Coast to open the Brighton Festival. Regular services for the luxury train commenced in May. © Chris
12th September 1991
The Folkestone Harbour branch in action: Hastings gauge Class 33 No. 33204 is depicted slogging up the 1 in 30 gradient in 1991 with a rake of sparkling Pullman carriages, forming the VSOE service to London Victoria. No. 33204 was one of about four Class 33 locomotives to be allocated to Railfreight Distribution, mainly being based at Dover Western Docks to shunt traffic on and off boats. © David Glasspool Collection
12th September 1991
On 12th September 1991, Standard Tank No. 80080 was seen at the rear of the ''Network Harbour Master'' shuttle special. The formation is depicted trundling down the Folkestone Harbour branch: the rolling stock in the background, which includes an EPB unit and a pair of spare BR Mk 1 carriages for the shuttle, mark the position of the main line. © David Glasspool Collection
Return to the Kent Rail Homepage or alternatively, check for Updates.
Website & Copyright information - Links - Contact the Webmaster
All content is copyright © David Glasspool unless otherwise stated