Gravesend Central



1st December 2013


1st December 2013 was scheduled to be the day of the lattice footbridge's removal. By 13:00, when the above was taken, the main span had already been lifted out and transported off site. © David Glasspool



1st December 2013


A large gap in the canopy makes the former position of the footbridge obvious. The staircases on both sides were still evident.© David Glasspool



22nd December 2013


On 22nd December work was underway lifting the track serving platform 1, to allow realignment in connection with this surface's eastward extension. The ''up'' through line, which the line of wagons can be seen upon in the above view, was due for permanent abolition. A ''Freightliner'' Class 66 was on site this day. © David Glasspool



 

<< Previous  Next >>

 


Return to the Kent Rail Homepage or alternatively, check for Updates.

Website & Copyright information - Links - Contact the Webmaster


 

All content is copyright © David Glasspool unless otherwise stated