Horsted Keynes
Bluebell & Primrose Line
The first line
planned for the area was that of the ‘’Ouse Valley Railway’’. This was to spur
off the Brighton main line just south of Balcombe, and assume a south easterly
heading through Uckfield, to meet the Hailsham branch (which was later extended
northwards to form the ''Cuckoo Line''). The scheme
had been instigated by the London Brighton & South Coast Railway, and although
it was acknowledged from the outset that this would be a loss-making venture, it
was nevertheless a necessary project. The company had watched with modest
concern in 1864, as the LC&DR submitted a Bill to Parliament for the
construction of a line into the heartland of the LB&SCR, Brighton, which was to
spur off the former’s Dover trunk route at Beckenham. However, it was when the
SER submitted a Bill to Parliament in the same year, for a line to Eastbourne,
that alarm bells began ringing in the LB&SCR camp. On 23rd June 1864, the latter
subsequently responded by acquiring Royal Assent for the building of the ‘’Ouse
Valley Railway’’ (OVR): the line’s sole objective was to provide a shorter route
for the LB&SCR between the capital and Eastbourne. The line’s success would not
be measured by passenger receipts, but rather, whether or not it prevented the
SER profiting from what was then a LB&SCR stronghold. Later in the same year,
however, talks between LB&SCR and SER Companies had been productive, so much
that the latter agreed not to go ahead with its Eastbourne plans; the OVR scheme
was also now obsolete, at least in the eyes of the SER.
Regardless of the SER’s retrenchment, the LB&SCR had other ideas, and much to
the annoyance of the former, Parliamentary Approval was received for the
building of a line between Hellingly, again on the ‘’Cuckoo Line’’, and St
Leonards. This was effectively an extension of the OVR, which was still very
much on the LB&SCR’s agenda, and provided the company with a shorter route
between London and Hastings. Construction of the OVR commenced in 1865, at the
Balcombe end of the route, and in the meantime, the SER pondered its next move.
The company responded to the LB&SCR’s actions in 1866, with the ‘’London Lewes &
Brighton Railway’’, a scheme it promoted jointly with the LC&DR. Royal Assent
was received on 6th August of that year, and the fifty-five mile line to the
Sussex Coast was to leave the LC&DR’s Dover route at Beckenham, construction
work costing a total of £3,000,000 (about £197,225,735 at 2007 prices). However,
in June 1866, London Discount Wholesale Bank ‘’Overend, Gurney & Company’’ went
into liquidation, with outstanding debts of £11,000,000. The bank had made
significant investments in railway schemes, including those mentioned, and over
ensuing months, these fell on stony ground. The LC&DR became insolvent, ending
the joint line scheme with the SER, and the LB&SCR wholly abandoned the OVR,
despite the beginning of works in the previous year.
A second railway scheme for this area of Sussex emerged a decade later. On 30th
November 1876, a Bill was deposited to Parliament for the formation of the
‘’Lewes & East Grinstead Railway’’, promoting a line between the namesake
locations. This proposal, which
received Royal Assent on 10th August 1877, was wholly independent of the LB&SCR,
and had instead been formulated by a group of local, and very wealthy,
landowners. Chaired by Henry Holroyd, the Third Earl of Sheffield and once a
Member of Parliament for the Conservative Party, the 20⅓-mile-long line was to
be double-track throughout, and serve extensive estates at Sheffield Park and
Newick & Chailey, the latter serving the residences of Reedens House and Newick.
In total, four substantial stations were planned for the route, which passed
through a sparsely populated area of rural Sussex: West Hoathly; Horsted Keynes;
Fletching & Sheffield Park; Newick & Chailey. This was truly a line built for the
convenience of a few select landowners, rather than local populations of
villages and towns. Building of the line was started by the independent ‘’Lewes
& East Grinstead Railway’’ (L&EGR), and the route was to be engineered by John Wolfe
Barry, whom had earlier carried out work for the SER in 1866, on the railway
bridge at Cannon Street. However, progress began to stall through lack of
capital, and the company called on the LB&SCR to assist with the scheme. Whilst
this may not have been a particularly profitable line for the LB&SCR to
eventually operate, the company was desperate to avoid the SER becoming
involved, perhaps in the aim of resurrecting its plans of 1866 for a line to
Brighton. The L&EGR was formally vested into the LB&SCR on 17th June 1878, the
latter assuming the construction task. By this time, two further stations had
been added to the list: New Barcombe and Kingscote. Facilities at the intermediate
stations were undoubtedly generous, particularly in light of the traffic levels
the route later saw, but economical measures were indeed made. The decision was
taken not to lay double-track between Horsted Keynes and what became Culver
Junction (south of New Barcombe), but infrastructure, such as the track bed and
bridges, would nevertheless be built to this profile to accommodate it, should a
second line later be required. Completion of building works came in July 1882,
and on 21st of that month, the line and stations were inspected to ensure the
infrastructure was constructed to the required standard before the route was
opened to passenger traffic. The first passenger services ran on 1st August of
that year, and the line became known colloquially as the ‘’Bluebell & Primrose’’.
Of the stations upon the route, that at Horsted Keynes, located a mile to the
north west of the village from which it took its name, was by far the most
extensive. The site was worthy of a place on the main Brighton trunk line,
rather than upon a countryside route built for use by a select few. Two islands
and one side platform, making a total of five platform faces, were in evidence
from the outset. Generous platform provision had been made here partly because
Horsted Keynes marked the commencement of the double-track section to East
Grinstead, but also in light of an impending branch from here to Haywards Heath,
on the Brighton Line. The three-mile double-track line opened on 3rd September
1883, and diverged from the existing line to Fletching & Sheffield Park at the southern end
of Horsted Keynes – crossovers between the two routes were also present
immediately north of the platforms. One intermediate station was provided at
Ardingly, and the northern section of the Bluebell & Primrose became a useful
diversionary route to Brighton – the advent of the Ardingly branch at least
meant that diverted services could avoid taking a circuitous route
through Lewes, to reach the coastal resort.
Track Plan of the current layout at Horsted Keynes. Click the above image for the full size version. Please note that this is a large drawing of
considerable width. Drawn by David Glasspool
June 1967
A northward view in 1967 shows the station to still be in fine fettle, the last BR train having left for Haywards Heath on 28th October 1963. The grass and shrubbery had for long been features of the platforms. The starting signals on the right-hand side were for the branch to Sheffield Park and had replaced an earlier timber-built arrangement. © David Glasspool Collection
June 1967
The fine ironwork of the island canopy's brackets can be appreciated in this southward view, which includes the ''dock'' line and starting signals seen in the previous photograph, in addition to the railings surrounding the subway entrance and the signal box. © David Glasspool Collection
June 1967
A southward view from what was originally the ''down'' island platform shows the former route to Lewes via Sheffield Park and Barcombe curving off to the left, whilst the branch which once led to Haywards Heath via Ardingly swings to the right. Of interest are the signs at the end of the platform, both dating from Southern Railway days; that on top warns about the third rail, which had gone by this time. © David Glasspool Collection
Next: The History Continues >>
Return to the Kent Rail Homepage or alternatively, check for Updates.
Website & Copyright information - Links - Contact the Webmaster
All content is copyright © David Glasspool unless otherwise stated