New Romney and Littlestone-on-Sea
For long, this area
has been associated with the narrow gauge Romney Hythe & Dymchurch Railway,
originally opened on 16th July 1927 and running on a track gauge of 15-inches.
The layout is extensive at New Romney, which boasts a four-platform station
covered by a 240-foot-long trainshed, in addition to locomotive and carriage
depots. However, probably unbeknown to the railway’s many visitors each year is
that a station serving a standard gauge branch line once existed no further than
80-yards south of the narrow gauge site. Today, there is no trace of this
station, the site having disappeared under a series of dreary industrial units;
it preceded its narrow gauge counterpart by over forty years.
The origins of New Romney and Littlestone-on-Sea, as the station was once known,
rest with the ‘’Lydd Railway’’, incorporated by an Act of 8th April 1881. This
authorised the construction of a single-track line, 10-miles in length, from
Appledore to Dungeness over Romney Marsh. Appledore had come into use as early
as 13th February 1851, on the SER’s first line to Hastings, which took a
circuitous route from the capital via Ashford. It was very soon relegated to
secondary status when through running to Hastings via Tunbridge Wells became
possible a year later, on 1st February 1852. Construction of the line was given
a window of five years and the ‘’Lydd Railway’’ agreed a working arrangement
with the South Eastern Railway for operating the trains. The SER’s Chief
Engineer, Francis Brady, was selected as engineer of the Lydd Railway. He had
held this position with the SER since 1st March 1870, after being promoted from
the role of Assistant Engineer on the death of his predecessor, Peter Ashcroft.
Progress was swift; the marshes by their nature were dead flat, requiring no
major earthworks. The line between Appledore and Lydd, a length of 7-miles and
6-chains, opened to all traffic on 7th December 1881. Beyond to Dungeness, the
line came into use for freight traffic only on the same day – indeed, the
extensive shingle plains of Britain’s only desert became a useful source of
ballast for the SER. Sights were set on rapid expansion and on 24th July 1882,
authorisation was granted for two new sections of line:
Appledore to Headcorn (length: fifteen-miles)
Branch line to New Romney (length: three-miles)
At the time, Dungeness was seen as having the potential to be developed into a
deep water port, where additional ferry connections with the continent could be
made. This inspired the Headcorn extension, which provided a shorter route to
the capital by cutting off the lengthy detour via Ashford. New Romney was a
market town and one of the Cinque Ports, 2˝-miles northeast of Lydd. As of 1861,
it covered an area of 2,919 acres and had a population of 1,062 (the latter of
which was recorded at 850 in 1827 and had subsequently increased to 1,328 by
1908).
To set the ball rolling, passenger services were extended from Lydd to Dungeness
on 1st April 1883. Next came the opening of the single-track-branch to New
Romney, on 19th June of the following year. This diverged from the Dungeness
line about 0.85-miles southeast of Lydd. At the junction, a curve of about
60-chains was formed to give the branch a northerly heading towards New Romney.
The terminus there was the branch’s only station from the outset, being named
‘’New Romney & Littlestone’’.
The terminus received an additional suffix early on in life, becoming ‘’New
Romney & Littlestone on Sea’’ in October 1888. The name ‘’Littlestone’’ derived
from a former rocky headland nearby called ‘’Little Stone’’, and the ‘’on-Sea’’
suffix came about as efforts to develop the locality into a neighbouring seaside
resort of New Romney began in the 1880s. Littlestone on Sea boasted a sandy
beach and its popularity started to grow towards the turn of the century.
The terminus itself was very much styled on the earlier-opened site at Lydd. Two platforms flanked either side of a run-a-round loop formation, the
tracks of which virtually ran north-to-south at this point. The western platform
was host to the main building, which was an attractive red-brick structure, a
variation of the design which had previously been seen down the line at Lydd and
Brookland stations. Single-storey and with a slated pitched roof, the station
building comprised arched windows and doorways. A gentlemen’s toilet block
extended from the building’s southern elevation, whilst from the eastern wall
was attached a neat canopy. The latter had a downward-sloping roof, a spiked
timber valance, and was supported by six stanchions. The opposing platform was
provided with a more modest structure in the form of a timber waiting shelter,
but even this was equipped with a spiked timber valance affixed to a
backward-sloping roof. Gas lamps were installed on both platforms.
On the western side of the lines could be found the goods yard. Here, four
sidings fanned out from a single connection with the incoming line from Lydd.
Early maps show one of these sidings to terminate at a turntable pit, whilst a
second served a dock platform and a third passed through a goods shed. An
important traffic here was livestock, sheep being moved in large quantities from
the marshes inland to prepare for the winter season. These details are better
illustrated in the below diagram, which also includes the former position of the signal
box, located north of the divergence of the goods line from the station
approach.
The independent Lydd Railway was absorbed into the SER in 1895. By 1907, the
run-a-round loop at the New Romney terminus had been extended southwards by
about 70-yards and the platforms also lengthened in the same direction. Minor
changes were also evident in the goods yard layout. On the advent of the
Southern Railway in 1923, more alterations followed, including the installation
of this company’s trademark barley-twist lampposts on the western platform. The
eastern platform fell out of use, the lampposts and waiting shelter being
permanently removed, and grass was allowed to take over the surface. A sturdy
brick-built water tower was erected in the fork of the diverging goods and
station lines.
As mentioned earlier, the 15-inch gauge Romney Hythe & Dymchurch Railway came
into existence in 1927. It initially ran between Hythe and New Romney, an
extension of the line being made to Dungeness via Greatstone in 1928, and was
double-track throughout. The RH&DR’s New Romney station resided a stone’s throw
from the SR’s site, just to the north west on the opposite side of the road (see
diagram for details). The standard gauge line from the SR station was extended
northwards across the road, to run parallel with the RH&DR platforms, forming a
private siding. This was used for RH&DR coal deliveries, brought in by rail via
the branch from Appledore.
Development of holiday homes along the coast between Dungeness and New Romney
during the 1930s encouraged the SR to re-align the branch line. Only the first
˝-mile of the original route from the terminus was retained, a new course for
the line being made nearer the coast. The junction with the Appledore to
Dungeness line was moved 1⅓-miles south east, inducing a sharp curve for trains
to negotiate when embarking on the branch. Two intermediate stations were
opened: Lydd-on-Sea and Greatstone-on-Sea. The former was situated ˝-mile from
the junction, comprising an island platform situated within a passing loop
formation; the latter had a single platform located 1˝-miles from the terminus.
The new single-track alignment opened on 4th July 1937; the original branch was
abandoned and the remaining 1˝-miles onto Dungeness became goods-only. It was
probably at this time that the signal box at New Romney closed and the signalman
was subsequently re-housed in a porch on the platform, which extended out from
the main building. Similar economies were enacted by the SR in the 1930s at
Martin Mill and Eynsford stations, where signal boxes were abolished and
replaced by lever frames installed within the booking offices.
The branch survived both World Wars unscathed, no cutbacks being enacted during
a time when other branches and stations were being culled, if only temporarily.
No doubt the fact that the area was very much military country, in a strategic
location, helped its survival. An army training camp had been established at
Lydd in the late 19th Century, which brought a large amount of military traffic
on the line from Appledore, and indeed this remains in existence today in the form of
a rifle range. The nearby RH&DR, which was taken over by the military in World
War II, again due to its strategic location, did suffer punishment, particularly
to the track. This was particularly true of that section between New Romney and
Dungeness, which had been run over by the army’s own tanks and bulldozers. The
double-track line re-opened between Hythe and New Romney on 2nd March 1946, but
the Dungeness section was not re-commissioned until 21st March of the following
year, and only as a single-track.
Goods services on the Dungeness spur ceased in early 1952, but trains to New
Romney remained – coal deliveries for the RH&DR continued and the station
enjoyed through passenger trains from Charing Cross on summer Saturdays. This
period of relative buoyancy started to disappear on the advent of the 1960s,
through a combination of increased car ownership, Phase 2 of the Kent Coast
Electrification, and of course the Beeching Report of 1963. The Hastings to
Ashford and New Romney lines were omitted from plans for third rail. Instead,
DEMUs in the form of Hampshire/Berkshire stock gradually started taking over
from steam traction on these routes from 1958. The death knell sounded with the
publication of the Beeching Report on 27th March 1963, within which the Hastings
to Ashford line was recommended as one of many line closures. As touched upon
earlier, this line had become somewhat of a backwater as early as 1852, when a
more direct route between Tonbridge and Hastings via Tunbridge Wells came into
use.
The end of steam traction on the South Eastern Division in 1962 saw the water tank upon
the tower at New Romney and Littlestone-on-Sea station removed. Goods facilities
at the terminus were formally withdrawn on 18th April 1964; coal deliveries to
the RH&DR also stopped coming by the Appledore route in this year. The final
blow was the complete closure of the New Romney branch on 6th March 1967,
including the withdrawal of passenger trains from all intermediate stations to
Appledore. The track was lifted in 1969 and the station building demolished in
the subsequent decade. The space vacated by the standard gauge siding, which was
once used for coal deliveries to the RH&DR, was absorbed into the miniature
operation in the 1970s. In the latter part of this decade, this railway’s New
Romney station was reconstructed on the siding’s former site, being built with a
substantially larger trainshed than previously.
What of the fate of the Ashford to Hastings line? Closure was scheduled for
1969, but this date then passed, reports being amended to reflect 1971 as the
year of service withdrawal. Thereafter, the route continued in a state of limbo, with
the cloud of closure hanging over it. The Appledore to Dungeness line, whilst no
longer catering for passengers, carried a new type of freight traffic for the
nuclear power station (operational from 1965), in addition to aggregate trains.
Eventually, economies were enacted to a much lesser extent by singling of the
route between Appledore and Ore in 1979, but today the Hastings to Ashford line,
plus most of the Appledore to Dungeness branch, remain intact.
1969
This northward view of the station, taken from the grassed-over eastern platform, was taken shortly after track lifting had finished. The toilets were once housed in the single-storey appendix of the main building, nearest the camera and bricked up. The vacant space to the left of the station structure was once host to a timber parcels shed. The signalman's ''porch'' can just be seen underneath the far end of the canopy. Today, not a brick remains. © Roger Goodrum
Return to the Kent Rail Homepage or alternatively, check for Updates.
Website & Copyright information - Links - Contact the Webmaster
All content is copyright © David Glasspool unless otherwise stated