London Victoria
Final Pre-Grouping Years
World War I came to a close in November 1918, and a degree of normality started
to return to Victoria. Dover was relinquished by the military and the SE&CR
finished construction work on the then new Marine station. Boat traffic between
the Channel port and Victoria resumed on 18th January 1919, on the
recommencement of the Dover to Ostend ferry service. On the 3rd of the following
month, continental trains also recommenced between Victoria and Folkestone, with
the restarting of the boat service to Bolougne.
1920 was a big year for the SE&CR station. It began with the completion of a
protracted re-signalling scheme which aimed to provide electrically-operated
points on all platform lines, right up to Grosvenor Road, in addition to a
series of three-position upper-quadrant semaphore signals, also worked
electronically. The contract for re-signalling the layout had been successfully
let to the ‘’British Power Railway Signal Company’’ prior to 1914, but the
subsequent war years led to inevitable delay. All equipment originated from the
United States, and was the first of its kind in Britain, being supplied by the
1904-founded ‘’General Railway Signal Company of Rochester‘’, New York. This saw
the commissioning of a new signal box, comprising 200 pneumatic pullout slides,
on the eastern side of the station, beyond the end of platform 1. As a result,
the peculiar ‘’Hole-in-the-Wall’’ of 1866 could be taken out of use. This
unusual installation was literally a recess in the eastern perimeter wall of the
station approaches, just south of Ecclestone Bridge, which comprised a
hotchpotch arrangement of levers added over time. The new signal cabin became
Victoria ‘’A’’, and it was complemented with the 42-lever Victoria ‘’B’’ box
alongside Grosvenor Road carriage sidings.
The new signalling came into use on 4th January 1920, and the SE&CR’s Victoria
was now more capable of handling several hundred train movements every day. This
prompted the transfer of all continental services of this company to the
terminus, on 8th of the same month. As a result, Charing Cross and Cannon Street
stations would never again see regular boat traffic, although it is true to say
that the latter had lacked such services since the outbreak of war in 1914.
Later, in 1922, the SE&CR lengthened the platforms.
Southern Railway Takeover
The SE&CR, LB&SCR, and VS&PR were all absorbed into the Southern Railway (SR) in
1923, in accordance with the ‘’Railways Act’’ of 1921, and the two Victoria
stations came under single ownership. The GWR retained its leasing rights to the
‘’Chatham’’ side of the terminus for a further ten years, despite the fact that
it had run no regular services from there since 1915. In 1924, the SR set about
uniting the hitherto separate stations into a whole, by cutting an archway in
the wall between concourses. This work was associated with further platform
alterations, which led to truncation of Eastern Section platform lines at their
northern ends by about 30-feet, to provide an enlarged circulating area. A
concrete-manufactured road incline was erected between Eccclestone Bridge and
the cab road between platforms 1 and 2, to maintain a constant flow of one-way
taxi traffic through the station. This eliminated the bottleneck at the ex-SE&CR
archway, caused by bi-directional running. A relic from LC&DR days was the
three-track arrangement separating platforms 6 and 8 on the station’s eastern
side (there was no platform 7). This was abolished by the SR, which resulted in
wider platform surfaces separated by just two tracks. As part of the same works,
exposed platform surfaces of the Eastern Section station were equipped with the
SR’s trademark Swan Neck lampposts. The station was united proper with the
renumbering of all platforms – ‘’Chatham’’ and ‘’Brighton’’ – from 1 to 17, east
to west, on 21st September 1925.
As mentioned earlier, the ‘’Brighton’’ side of Victoria had been host to
electric services since the conversion of the South London Line to overhead wire
operation in 1909, trains running on alternating current of 6,600 Volts supplied
from the Deptford Power House of the London Electric Supply Corporation. Crystal
Palace had been reached from Victoria by electric trains in May 1911, and this
had involved electrifying as far south as Norwood Junction and Selhurst, where
workshops and berthing sidings for electric stock were located. In 1913, the
LB&SCR set about further electrifying its suburban network, which involved
taking the wires beyond Balham to Coulsdon & Smitham Downs (later ‘’Coulsdon
North’’), and to Sutton via Selhurst. These efforts were, however, stifled by
World War I, which brought a halt to the programme, but the scheme was revived
after the conflict. The task in had was to finish off the semi-complete
infrastructure works to bring the wires to Coulsdon & Smitham Downs, in addition
to making an extension of the electrification scheme to Brighton and Eastbourne.
Work spilled over into Southern Railway ownership, and although this company had
decided to pursue the LSWR’s 600V D.C. third rail system for any further
electrification schemes, the decision was made to complete the Coulsdon &
Smitham Downs and Sutton projects with overhead wires, given the already
advanced stage of the infrastructure works. Electric services over these routes
commenced on 1st April 1925; in the meantime, no works had begun on southward
electrification to the Sussex coast and, consequently, overhead wires did not go
beyond Coulsdon North.
In August 1926, the SR Board announced the complete abolition of the LB&SCR’s
overhead wire system, for it was incompatible with the existing third rail
arrangement of the LSWR, the latter of which was also in the process of being
used to electrify Eastern Section lines. As a result, the South London Line
became D.C. operation on 17th June 1928, as did the loop route between Victoria
and London Bridge via Streatham Hill and Crystal Palace. Victoria to Crystal
Palace services remained in AC format until 3rd March 1929. The last AC
departure from Victoria was the 00:10 to Coulsdon North, on Sunday 22nd
September 1929 – DC services had already commenced along the route by this time.
On 27th February 1930, the Chairman of the SR announced the electrification of
the main line to Brighton and Worthing, taking the 660 Volts D.C. third rail
36-route miles beyond Coulsdon North (track miles: 162½). The scheme would
partly be funded by money saved as a result of the 1929 abolition of passenger
duty on First and Second Class fares. Further shortfalls in funding could later
be made up with an increase in passenger receipts, as a result of an improved
electric service. Lines between Purley and Brighton would be re-signalled using
three-aspect colour lights, Haywards Heath station completely rebuilt, and new
signal boxes brought into use at the latter and Brighton. In addition, a new
130-lever frame was to be installed in the existing cabin at Three Bridges, and
the entire scheme was estimated to cost £2,700,000. The new signalling system
was brought into use piecemeal:
Coulsdon North to Balcombe Tunnel Junction (via Quarry Line): 5th June 1932
Balcombe Tunnel Junction to Copyhold Junction: 6th October 1932
Copyhold Junction to Haywards Heath: 12th June 1932
Haywards Heath to Preston Park North: 9th October 1932
Preston Park North to Brighton: 16th October 1932
Electric trains commenced between London and Brighton on trial runs on 2nd
November 1932 – electric services had been running as far as Three Bridges since
17th July of that year. On 30th December 1932, the Brighton electrification
project was formally deemed complete with ceremony, and on 1st January of the
following year, normal public services using electric stock commenced. This
provided Victoria with four electric services to Brighton every hour, three
stopping and one fast. With reference to ‘’fast’’ services, every train ran with
a Pullman car, and three of these daily departures from Victoria were wholly
Pullman in their constitution – naturally, these services were those of the
‘’Southern Belle’’. These trains used platform Nos. 12 and 13. Much more detail
concerning this prestigious service can be found within the pages of the VSOE
British Pullman: Fleet Review section, save regurgitating it here, but it is
worth mentioning that it was know as the ‘’Brighton Belle’’ from 29th June 1934.
The Brighton project was quickly followed up by the completion of yet another
electrification scheme, that of the lines to Eastbourne and Hastings (Central
Section), at an estimated cost of £1,750,000. Early works had begun alongside
the Brighton scheme, commencing with the complete rebuilding of Hastings station
in 1931. The Seaford branch was to receive third rail, and proposals included
the novelties of electrifying the Copyhold Junction to Horsted Keynes spur and
beyond the station at Hastings, to Ore. The former was to accommodate the stock
of the proposed Seaford to Haywards Heath electric service. This would have used
up precious platform capacity at Haywards Heath, thus the solution was to extend
the service to Horsted Keynes, which could spare an entire island surface. At
Hastings, room was not available to build a carriage shed to service electric
stock, thus it was decided to construct this at Ore, where a large expanse of
land existed beside the goods yard. Scheduled electric services commenced to
Eastbourne and Hastings from London on 7th July 1935. They had been preceded by
the ceremony formally deeming works complete, on 4th of the same month, and
trial running of electric units had been ongoing since May.
The third and final electrification scheme to mention is that encompassing the
lines to Portsmouth, via Horsham, including the Bognor Regis branch. An
estimated £2,750,000 was to be spent on electrifying approximately
165-track-miles and, in places, commissioning three-aspect colour lights. The
public electric timetable over these lines came into use on 3rd July 1938.
Crucially, the three schemes combined – Brighton, Hastings, and Portsmouth –
eliminated the vast majority of steam traction from the Central Section
platforms at Victoria.
Eastern Section Matters
Unlike Western and Central Sections of the SR’s network, the Eastern territory
was wholly without any form of electrification. The SE&CR Joint Managing
Committee had, by 1920, produced a plan detailing which lines it proposed to
electrify, and the scheme would be implemented when capital was available. SER
and LC&DR companies had for decades run their networks on a shoestring, the
latter more so than the former, and by the advent of the SR, nothing had been
done on the electrification front. In 1924, the SR commenced work on laying
third rail along the following routes:
Victoria to Orpington, via Herne Hill, Bromley South, and Bickley Junction
Holborn Viaduct to Herne Hill
Catford Loop Line
Crystal Palace (High Level) branch
11,000 volts of alternating current was sourced from the ‘’London Electric
Supply Corporation’’ and distributed to local substations from a huge switch
room at Lewisham. The latter was a colossal three-storey-high red brick affair,
constructed around a steel frame, and could be found at the foot of the railway
embankment to the west of Lewisham station. Scheduled electric services on all
above routes commenced on 12th July 1925, these trains using platforms 3, 4, and
6 of the Eastern Section. Colour light signalling later came into use between
Holborn Viaduct and Elephant & Castle on 21st March 1926, but semaphore signals
were retained on the approaches to Victoria. As earlier mentioned, the latter
were a then recent installation, having been brought into use by the SE&CR on
4th January 1920.
On 17th November 1924, the SR commenced a range of new daily Pullman services
from Victoria, serving the coastal resorts of Thanet and the Port of Dover. The
train for the latter was nicknamed the ‘’White Pullman’’, because of the Umber
and Crème livery of the carriages; at this time, other Eastern Section Pullmans
remained in the Crimson Lake livery of the SE&CR. On the opposite side of the
Channel, the French inaugurated the ‘’Flèche d’Or’’ all-Pullman train, between
Calais and Paris. The first services ran on 11th September 1926 and comprised
two trains, each ten-vehicles in length. These were formed of British Pullman
vehicles built by the Birmingham Railway Carriage & Wagon and Metropolitan
Carriage Wagon & Finance Companies. Officially, the SR’s Pullman service to
Dover was called the ‘’Continental Express’’, but in spite of this, passengers
referred to it as the ‘’Golden Arrow’’, the English translation of the French
train. As a result, the service was officially re-launched as the ‘’Golden
Arrow’’ on 15th May 1929, and the train normally departed from Victoria’s
platform 8 at 11:00 AM. In the previous year, platform information systems at
the terminus had been modernised by the installation of three manual indicator
boards: two on the Eastern Section concourse and one on the Central Section
concourse. With reference to those on the Eastern side of the station, one
indicator board displayed departure times for Kent Coast and suburban trains,
whilst the second board was dedicated wholly to Continental boat services.
Canopies of riveted steel construction had also been erected over the platforms,
beyond the extent of the trainshed, in 1930.
In the meantime, further suburban electrification had been pushed through with
great haste. All three North Kent routes to Dartford had seen their first
electric services between 10th and 16th May 1926 during the General Strike; the
full suburban electric timetable commenced on 6th June of that year. Since 28th
February 1926, electric services had been running to Orpington from the ex-SER
termini of Charing Cross and Cannon Street. Of particular relevance to Victoria
were the Sevenoaks and Maidstone electrification schemes. The former was
authorised in 1934, and involved extending third rail on the ex-SER route beyond
Orpington, to Sevenoaks Tubs Hill. In addition, electric trains were also to
reach Sevenoaks by means of the ‘’Chatham’’ line; the scheme included the laying
of third rail beyond Bickley Junction, and onto St Mary Cray, Swanley Junction,
and the Bat & Ball branch. The Bickley Junction to St Mary Cray section was
opened to public electric traffic first, on 1st May 1934; these services were
extended to Sevenoaks Tubs Hill on 6th January of the following year, via both
Orpington and Bat & Ball routes. Finally, we come to the Maidstone scheme, which
involved the electrification of 117-track-miles of line. On the ‘’Chatham’’
line, third rail was extended beyond Swanley Junction to Gillingham, the latter
of which became the outer limit of suburban electrification on this route. Of
Maidstone itself, the town had the good fortune of being served by two routes:
that of the Medway Valley Line, between Strood and Paddock Wood, and also the
latterly-conceived appendix off the Bat & Ball route, serving what is now the
‘’East’’ station. Third rail was extended from Gravesend Central to Maidstone
West, and from Otford Junction to Maidstone East, and public electric services
commenced on 2nd July 1939. Throughout most of the day, Victoria had an hourly
service to Gillingham and Maidstone. Essentially, this started as just a single
train at the terminus, which subsequently split into Gillingham and Maidstone
portions at a new Swanley station.
Brief mention should also be made of the ‘’Night Ferry’’, which, at the time,
became Britain’s only proper ‘’through’’ train to the continent, running between
London and Paris. It differed from other boat trains, such as the ‘’Golden
Arrow’’, by the fact that the carriages crossed the Channel with the passengers,
on purpose-built vessels. The train comprised sleeping carriages owned by the
‘’Compagnie Internationale des Wagons-Lits’’ (International Sleeping Car
Company), which had been tailor-made to fit the British loading gauge. Thus,
passengers would board the train at Victoria and not disembark until reaching
Paris Gare du Nord. Standard non-sleeping carriages were also part of this
train, and these did not cross the water. The service began on 14th October 1936
and the first train left Victoria at 10 PM, with an estimated journey time of
eleven hours via Dover and Dunkerque.
January 2003
A 4 CEP is stabled alongside platform 5, which since 1985 has seen its southern end covered by a car park
upon struts. On the far right, we see the shopping centre which covers the northern half of the Central Section
platforms and, on the left, the offices which are built over the latter's southern ends. © David Glasspool
January 2003
These are the lesser-seen SE&CR offices situated along ''Wilton Road'' which, like the main façade, are faced
in Portland Stone. On the extreme left, in the background, can be seen the Eastern Section station's crème
brick offices, which date from 1862. © David Glasspool
15th June 2004
The trainshed spans have featured blue tarpaulin over their glazed areas for many years, but this is set to change
with the commencement of a restoration programme, in December 2008. This view shows 4 Vep No. 3452 stabled
in platform 6 after arriving with a stopping service from Faversham. © David Glasspool
15th June 2004
The Victoria approaches are seen from the western extremity of the Central Section tracks. On the far left is
the former ''Imperial Airways'' terminal which, as seen here, was partially extended over the tracks. In the
centre is the earlier mentioned office block, completed in 1991, whilst in the distance can just be seen one of
the trainshed arches of the Eastern Section station. © David Glasspool
22nd October 2004
A second view of the approaches, this time from up high, better shows the connection between Central and
Eastern Section metals. Elizabeth Bridge is in view, which is still host to staircases providing access to the
Central Section platforms for engineers. © David Glasspool
<< Previous Next: The History Continues >>
Return to the Kent Rail Homepage or alternatively, check for Updates.
Website & Copyright information - Links - Contact the Webmaster
All content is copyright © David Glasspool unless otherwise stated