London Victoria
SE&CR Follows Suit
The LC&DR had formed a Common Managing Committee with the SER in 1899, becoming
known jointly as the South Eastern & Chatham Railway (SE&CR). The opening of the
first section of the rebuilt ‘’Brighton’’ station at Victoria in 1906 prompted
the SE&CR to make improvements to its own terminus, which it continued to lease
jointly with the GWR. Unlike the LB&SCR’s scheme, which had involved razing all
existing structures, bar the Grosvenor Hotel, to the ground, the SE&CR’s
programme largely saw the retention of the 1862 terminus, but included tasteful
additions to the northern façade. In comparison to the ‘’Brighton’’ station,
signalling was not drastically altered, and points and semaphores continued to
be controlled from a recessed frame within the station’s eastern elevation.
Dubbed the ‘’hole-in-the-wall’’, this basic signal cabin had originally come
into use with the first wave of improvements enacted at both termini over the
period 1865 to 1867. Its complement of levers was subsequently extended as part
of the 1907 to 1908 works, and both it and the ‘’Chatham’’ yard signal box,
overlooking Grosvenor Carriage sidings, survived the SE&CR improvement works.
The ‘’Chatham’’ yard also received a 54-foot 10-inch locomotive turntable at the
time of the SE&CR scheme.
Work began in 1907 with the demolition of the clapboard structures fronting the
station to the north. Overseeing the entire project was Mr Percy C. Tempest,
engineer of the SE&CR Managing Committee, and architect M. W. J. Ancell. Mr
Tempest’s architectural assistant, Mr A. W. Blomfield, was responsible for
producing the new station frontage, which would face onto the main forecourt and
extend around the corner to Wilton Road. Messrs Higgs and Hill were hired as
building contractors, and the construction task was not without its problems.
The fact that the station stood on a site formerly occupied by a canal basin
made it difficult for contractors to lay solid foundations. This problem was
solved by forming a large raft of reinforced concrete, 6-feet thick and
measuring 200-feet in length by 65-feet in width, and placing this upon the site
destined for the new building. The latter transpired to be four-storeys-high,
and had a 170-foot long frontage facing onto the station forecourt, and a
200-foot-long block fronting Wilton Street. It was fundamentally Georgian in
style, combining some French influences, and on its northern façade was faced
with Portland Stone. The southern elevation, facing the platform concourse, had
a red brick finish, of which the window openings were lined with Portland Stone.
The new structure, graced with a centrally-positioned arch for cab access,
housed many rooms, most of which were for public use:
New range of lavatories
Telegraph office
Large ambulance classroom (for staff use), situated above telegraph office
Battery rooms (in connection with the telegraph room)
New offices for Continental Traffic Department
Cloakroom
Storeroom (above cloakroom, and connected to it by means of a hydraulic lift)
Tearoom
Booking office dedicated to Crystal Palace traffic
Buffet and lounge
First Class refreshment bar
Third Class refreshment bar
General waiting room (with attached lavatories)
Hairdresser’s shop, with dressing rooms (situated upon mezzanine floor on the station’s western side)
First floor restaurant, measuring 160-feet by 38-feet
Basement restaurant, measuring 100-feet by 56-feet
Both restaurants were occupied by Messrs. Joseph Lyons & Co, who had been the
contracted caterers for the LC&DR for a number of years. One of the aims of the
improvement programme was to increase the circulating space at the head of the
platforms. This had previously been obstructed by pillars supporting the low
roof which spanned the gap between the timber frontage buildings and the
trainshed. The gap in-between the trainshed and the new masonry structure was
subsequently filled by a ridge-and-furrow patterned roof, carried upon girders
that rested on the walls of the new building and on the roof pillars standing on
the platforms themselves. 4-feet of space was gained by reducing the width of
the frontage building, compared to the area taken up by the timber affairs, and
the lengths of platform Nos. 6 and 7 were cut back by 15-feet. The twin-span
Fowler trainshed was renovated, and the original brick-built offices on the
eastern side of the station were retained along Wilton Road, these containing a
Royal Suite, booking hall, waiting rooms, and a baggage office. Much of the new
station had been completed by July 1908, parts being opened piecemeal. On 16th
November of the same year, both the LB&SCR and SE&CR officially sanctioned the
introduction of ‘’Electrobuses’’ into their station forecourts, a privilege
denied to all other forms of mechanically-driven omnibuses.
After the 1865 to 1867 widening works of the LB&SCR and LC&DR Companies, the
‘’Chatham’’ station comprised nine platform faces serving nine tracks, two of
these being mixed gauge to accommodate GWR services. The GWR completely
abandoned Broad Gauge on their entire network in 1892, and the SE&CR’s
rebuilding of Victoria provided a total of ten platform faces under Fowler’s
twin-span roof, all serving standard gauge lines.
The Brighton’s ‘’Elevated Electric’’
In 1891, official figures showed that the South London Line was carrying six
million passengers per annum, with trains running at about six minute intervals
on weekdays. At the turn of the century, LB&SCR traffic became increasingly
threatened by the electrification of tramways within the London suburbs. The
company’s response culminated in Parliament authorising, in 1903, the
electrification of any part of the LB&SCR network. On the advice of Philip
Dawson, Consulting Engineer to the LB&SCR, it was decided to pursue an overhead
electric wire system which, it was argued, avoided complicating the permanent
way with conductor rails. The South London Line was selected as the test bed for
the new system. In December 1905, it was announced that the ‘’British
Thomson-Houston Company’’, in association with the Berlin-based ‘’Allgemeine
Elektricitäts Gesellschaft’’, had been awarded the contract to electrify the
nine-mile route. The Thomson-Houston Company owned the patents for the proposed
‘’Winter-Eichberg’’ single-phase system proposed. Manufacture of components was
to start in Germany first; this was because the Allgemeine Elektricitäts
Gesellschaft company had already made motors identical to those proposed for use
on the South London Line electrification, thus equipment could be acquired
quickly. Manufacture of British components eventually commenced in Rugby, and
electrification work began in 1906.
Seven of the roads at Victoria (LB&SCR) were electrified: platforms Nos. 1 to 5,
and the middle lines in-between platform Nos. 3 and 4, and in-between Nos. 5 and
6. Electrification of the route took twice as long as expected, and it was later
claimed this was due to the fact that the LB&SCR’s advisors had failed to grasp
the difficulty of installing a brand new infrastructure system on a line which,
at the same time, still had to handle substantial suburban traffic. By October
1909, the electrified section of line in-between Victoria and Peckham Rye had
been formally approved by the Board of Trade, but the remaining stretch beyond,
to London Bridge, had not. Initially, there was speculation that the overhead
wire gantries obscured signals, hence the Board of Trade’s foot dragging, but
this transpired not to be the case. There had, however, been mechanical
interference between the signals and overhead wires at London Bridge, a problem
which was later rectified by the building contractor Messrs R. W. Blackwell & Co
Limited of Westminster. Electric services between Victoria and London Bridge
formally commenced on 1st December 1909, running on 6,600 Volts A.C. overhead
wires. Steam-hauled services were retained on the South London route during the
early hours on weekdays, running between 4:30 AM and 7:30 AM. Before
electrification, the impressive per-annum traffic level of six million
passengers in 1891 had increased by a further two million at the turn of the
century, only to drop down to four million in 1908, as a result of tramway
competition. This fall was later reversed after the new services began, with 7½
million passengers being recorded on the route during the first full year of
electric working. The early morning steam services were totally abolished from
the route on 1st June 1912.
After the promising start on the South London Line, the LB&SCR swiftly proceeded
with further electrification. The next candidates for the scheme were those
routes to Crystal Palace, from Victoria and London Bridge. Overhead catenary was
installed over the route via Streatham Hill for Victoria services, whilst for
London Bridge trains, the wires were extended down from Peckham Rye. The
electric system extended as far south as Norwood Junction and Selhurst, where
berthing sidings and a depot existed to maintain the fleet of electric multiple
units. The Victoria via Streatham Hill route was the first to be commissioned
for electric trains, the these services running to Crystal Palace from 12th May
1911. This coincided with the opening of the ‘’Festival of Empire’’ at the
Crystal Palace by King George V. Electric services from London Bridge, via
Peckham Rye and Tulse Hill, did not start until the following year as a result
of a lack of power supply for this section. The first such trains from this
terminus ran on 1st March 1912, exactly three months earlier than scheduled, due
to a coal miners’ strike.
World War I and Continental Services
The outbreak of war in August 1914 signalled a busy time for Victoria. Whilst
standard passenger services were to decline, the volume of traffic handled at
the terminus was to increase substantially. The station became the main London
hub for the dispatch of troops to the continent, and at the other end of the
line, Dover, the railway docks came under military control. The semi-complete
Dover Marine terminus was hastily brought into use to handle ambulance trains –
at this time, the station comprised a wrought-iron trainshed, but lacked walls
and platforms, and building work was not completed until 1919. Suspension of
continental services between all SE&CR London Termini and Dover was immediate.
Continental traffic continued to Folkestone, which at this time retained boat
crossings to the French ports of Boulogne and Dieppe. From 15th November 1914,
all such rail services were concentrated at Victoria – as a consequence, Cannon
Street and Charing Cross stations lost all their continental traffic. This
scenario became permanent for Cannon Street, but Charing Cross regained boat
services for a brief period during 1919, until all such traffic was transferred
to Victoria as of 8th January 1920.
Inter-company passenger services were also to disappear from Victoria during the
war years, never to be seen again. Regular GWR trains from the SE&CR station
ceased on 21st March 1915, but the former still remained a joint lessee of the
terminus far into the Southern Railway era. GNR and Midland Railway services had
stopped long before this, in October 1907 and June 1908 respectively. The LB&SCR
station retained LNWR passenger trains a little longer, these being removed from
the timetable in September 1917.
Civilian boat traffic between Victoria and Folkestone ceased on 13th April 1916,
on the withdrawal of the Dieppe crossing; Boulogne had been abolished as a
destination in November of the previous year. Hitherto, the Dieppe service had
been dealt with at Newhaven, but transfer to Folkestone had occurred immediately
on the outbreak of war. For over four years, the SE&CR’s Victoria became a
terminus bustling with troops, 24-hours a day, seven days a week: some soldiers
were returning on leave, whilst many others were heading off to Dover, bound for
the continent. At the time it was reported that Regimental officers and troops
were bundled into badly lit carriage compartments of ten seat capacity, arranged
in the form of five seats either side. By contrast, First Class coaching stock,
complete with dining cars, was provided for red-tabbed officers, complete with
seat reservations.
Victoria did not escape attack during World War I, but compared with the much
more powerful air raids of the subsequent 1939 to 1945 conflict, the damage was
minor. On 28th November 1916, a German ‘’Air Transport Company’’ aircraft
dropped ten 20 lb bombs on the terminus and nearby ‘’Brompton Road’’, in a
failed attempt to strike Admiralty buildings to thwart Britain’s war campaign.
The crew of the aircraft were captured in France on the return leg, when engine
trouble forced the pilot to ditch the plane.
12th February 1987
This view of Class 73 No. 73130 clearly shows one of the flights of stairs which provided the
Central Section platforms with a direct pedestrian link to Ecclestone Bridge. The Gatwick
Express carriages can be seen disappearing into the darkness beyond the bridge span; the
northern halves of the platforms had been built over by this time.
© David Glasspool Collection
21st October 1990
''Celebrity'' 4 SUB No. 4732 is seen stabled at platform 7, Eastern Section, forming a shuttle service to the
Streatham Hill Depot Open day. Suspended above the unit is the then recently completed car park, adjacent
to the main shopping centre which now covers the Central Section platforms. © John Horton
1st November 1991
No. 73235 is seen ''under the raft'', at a time when the Gatwick Express had a dedicated pool of locomotives.
This locomotive survived privatisation and became a ''Thunderbird'' for operator ''South West Trains''.
© David Glasspool Collection
1992
A 12 CEP formed of unit Nos. 1513, 1610, and 1620, is seen standing on the signal protecting the approach to
Victoria. This is the stock for the 17:13 Victoria to Ramsgate via Chartham, which has come empty from Stewarts
Lane. On the far left is the spur to Grosvenor Carriage Shed. © John Horton
<< Previous Next: The History Continues >>
Return to the Kent Rail Homepage or alternatively, check for Updates.
Website & Copyright information - Links - Contact the Webmaster
All content is copyright © David Glasspool unless otherwise stated