Nunhead

 

In addition to a new station, a three-storey-high substation was erected within the fork of Nunhead Junction. This comprised a steel frame, surrounded by red brick, and housed three 1500kW rotary converters. The original goods yard here remained in situ, along the northern side of the running lines, beside the former site of the first station. However, it was now overlooked by a new 38-lever signal box, built on the ‘’up’’ side of the running lines, again beside the old site of the LC&DR station. The cabin was built to an in-house SR design, although showed traces of those much earlier signal boxes built by Saxby & Farmer in the late 19th Century.

Electrification of the Charing Cross lines in February 1926 caused problems for goods traffic, which remained substantial from north of the Thames. Until this time, the Hither Green freights which came through Blackfriars were routed onto ex-SER lines via London Bridge and New Cross. The accelerated timetable made it difficult to slot slow freights in-between fast passenger services. The solution lied with the defunct Greenwich Park branch. At this time, the line remained virtually complete; the section between Nunhead and Brockley Lane was still serviceable, since freights continued to use the LNER goods depot at the latter. Beyond, the line was complete, but in a severe state of decay. The decision was taken to restore the double-track between Nunhead and the closed Lewisham Road station. Thereafter, a completely new spur would connect the line with ex-SER rails at Lewisham Junction. The spur was to be carried over the Lewisham avoiding lines upon a huge lattice girder span of steel construction. The refurbished line came into use on 30th June 1929, and it was dedicated to freight traffic from the outset, thus lacked third rail. It was signalled throughout with four-aspect colour lights, but semaphores were retained at Nunhead Junction.

During 1935, third rail was laid along the Nunhead to Lewisham connection and public electric services commenced over the line on 30th September of that year. A boom in passenger traffic as a result of electrification required additional trains to run on all three North Kent routes from Dartford. Of those peak-hour St Paul’s services which ran on Bexleyheath and Sidcup lines, it was decided to divert a number onto the spur at Lewisham and through to Nunhead, freeing up capacity on the London Bridge approaches.

The Crystal Palace branch suffered a second period of wartime closure between 22nd May 1944 and 4th March 1946. On absorption into British Railways in 1948, the days of the line were clearly numbered. Even before the destruction of Crystal Palace by fire in November 1936, passenger numbers had been consistently low, and the general locality was thought to be better served by the Central Division line through the Low Level station. The last timetabled services ran along the Crystal Palace branch on Saturday 18th September 1954, and this became one of very few electrified lines to close. Little under five years later, signalling alterations took place at Nunhead in connection with the Kent Coast Electrification. Colour light signals replaced semaphore signals between Factory Junction and Nunhead on 8th March 1959, and between the latter and Ravensbourne on Sunday 22nd of the same month. Signal boxes at Crofton Park and Catford were abolished, but that at Nunhead retained to control the new signals. For this purpose, a relay room came into use beside the signal box’s western elevation.

Nunhead goods yard dated back to the original LC&DR station and its closure finally came on 2nd April 1962. Beyond this date, freight traffic was still handled at Brockley Lane on the Lewisham connecting line, but this too ceased on 4th May 1970. Advancements in signalling over a decade later saw Nunhead signal box decommissioned: its functions were taken over by the Victoria Panel (located at Clapham Junction) on 17th January 1982. Partial station reconstruction in 1989 saw the island rebuilt in prefabricated concrete and the incorporation of a ticket booth upon it. This allowed the booking hall at street level to be taken out of use. The red brick building was subsequently demolished and the station entrance opened up.

 


23rd February 2007

 

Shortly after the Class 37s' cameo appearance, Class 60 No. 60095 appeared with the Acton to Cliffe empty

Brett hoppers. Since the line through Snow Hill Tunnel ceased to be used by cross-London freights on 23rd

March 1969, such trains from north of the Thames have been required to travel via the West London Line

and Clapham Junction. David Glasspool

 


23rd February 2007

 

''Networker'' No. 465182 had arrived from London Victoria with a Dartford service. This unit has since been

fitted with new traction drive by Hitachi, which aims to improve unit reliability. The work took place on all

Class 465/0 and 465/1 units at the company's Ashford depot between April 2009 and April 2010. David Glasspool

 


 

<< Previous

 


 

Return to Index

 


Return to the Kent Rail Homepage or alternatively, check for Updates.

Website & Copyright information - Links - Contact the Webmaster


 

All content is copyright © David Glasspool unless otherwise stated